Project Twin — PTU-2026-017
Nusantara Energi · CT-2026-0142 rev B · CFG-P40-3312 (platform P40)
Delivery commitment 15 Nov 2026 is at risk. Current forecast 27 Nov 2026, 12 days late.
Data quality
- HighSupplier forecast for MR-01 was corrected after the recovery decision was taken (EV-3007 supersedes EV-3005).
- MediumProduction execution projection last published 2 days ago by MES. Freshness AGING.
- LowInvoice readiness is COMPUTED from contract milestones; finance system of record not yet integrated.
Committed delivery 15 Nov 2026 — no authorized change
Forecast is 12 days beyond the committed date. The commitment itself is unchanged.
History (2)
- 13 Aug 2026, 16:12 UTCForecast moved 15 Nov → 27 Nov after supplier correction
- 10 Aug 2026, 07:20 UTC · supersededForecast moved 15 Nov → 20 Nov after supplier delay notice
Baseline ER-P40-3312-R2 RELEASED and applicable
MR-01 HV switchgear NOT_READY — supplier forecast 12 Oct 2026
Forecast is 22 days beyond the committed date. The commitment itself is unchanged.
History (3)
- 13 Aug 2026, 16:12 UTCForecast 05 Oct → 12 Oct (EV-3007 supersedes EV-3005)
- 10 Aug 2026, 07:20 UTC · supersededForecast 20 Sep → 05 Oct declared by supplier
- 12 Jun 2026, 09:00 UTCSupplier committed 20 Sep 2026 on PO 4500219871
History (1)
- 10 Aug 2026, 07:35 UTCPARTIALLY_READY → NOT_READY, blocker MR-01
Work order release blocked by material readiness
Forecast is 15 days beyond the committed date. The commitment itself is unchanged.
FAT forecast moved to 10 Nov 2026; procedure rev C outstanding
Forecast is 11 days beyond the committed date. The commitment itself is unchanged.
Delivery forecast 27 Nov 2026 exceeds commitment by 12 days
Forecast is 12 days beyond the committed date. The commitment itself is unchanged.
Milestone invoice readiness pending delivery evidence
The Twin projects state published by the owning modules and never mutates it. Editing a value here would be rejected and routed to that module's command contract.