Exception & decision inbox
Meridian Switchgear moved the MR-01 forecast from 20 Sep to 05 Oct, then corrected it to 12 Oct 2026. The committed date is unchanged.
MR-01 is a governed dependency of production start, FAT and the 15 Nov delivery commitment. Readiness fell to NOT_READY and the delivery forecast moved 12 days beyond commitment.
Select a recovery alternative within authority and record the decision.
- · Customer delivery commitment 15 Nov 2026
- · FAT completion 30 Oct 2026
- · Milestone M4 invoice readiness
Detected 10 Aug 2026, 07:41 UTC · due 18 Aug 2026, 17:00 UTC
Decision path — the alternatives carry different consequences, so a human authority must choose.
- EMAILEV-3005Meridian Switchgear delay notice, new forecast 05 Oct 2026MAIL · 10 Aug 2026, 07:20 UTC · sha256:ev3005…
- EMAILEV-3007Meridian Switchgear revised forecast 12 Oct 2026 (supersedes EV-3005)MAIL · 13 Aug 2026, 16:12 UTC · sha256:ev3007…
How should GSPE recover the 15 Nov 2026 delivery commitment given the MR-01 supplier delay?
Deadline 18 Aug 2026, 17:00 UTC · authority required: Procurement Lead — Expedite spend up to IDR 250 m on project PTU-2026-017
- MANDATORYApproved-source constraintMR-01 may only be sourced from a supplier holding a valid IEC 62271-200 type-test certificate on the approved source list.CON-IEC-62271 · QMS ASL-2026-118
- MANDATORYContractual delivery dateDelivery after 15 Nov 2026 incurs liquidated damages at 0.5% of contract value per week.CON-CONTRACT-4.2 · CT-2026-0142 §4.2
- POLICYExpedite spend authority capExpedite spend above IDR 250 m requires Commercial Director authorization.CON-EXPEDITE-CAP · Delegation of authority matrix 2026
Accept the corrected supplier forecast and re-plan downstream milestones.
- SCHEDULE− Delivery slips to 27 Nov 2026
- COST− Liquidated damages ~IDR 214 m
- CUSTOMER− Commitment breach on first PTU delivery
Pay expedite premium to Meridian Switchgear and book priority air freight to pull MR-01 back to 26 Sep 2026.
- SCHEDULE+ Delivery recovers to 17 Nov 2026
- COST− Expedite premium and freight IDR 186 m
- RISK− Supplier has met 2 of 4 previous expedite promises
Agent recommendation. It stays a proposal until deterministic validation and human authorization; the agent cannot execute it.
Source MR-01 from Delta Electro, who can deliver on 18 Sep 2026 at lower cost.
- SCHEDULE+ Delivery recovers to 15 Nov 2026
- COST+ Saves IDR 92 m against the current purchase order
- COMPLIANCE− Delta Electro holds no IEC 62271-200 type-test certificate and is not on the approved source list
Eliminated by mandatory constraint CON-IEC-62271. Economic or schedule benefit cannot make it selectable.
Agent recommendation. It stays a proposal until deterministic validation and human authorization; the agent cannot execute it.
Build and test the skid without MR-01, then retrofit the switchgear before shipment.
- SCHEDULE+ Delivery recovers to 21 Nov 2026
- QUALITY− Requires a second partial FAT and Engineering Authority sign-off
- RISK− Retrofit on a tested skid has no precedent on the P40 platform
Decision recorded
Only feasible option that holds the contractual date within procurement authority. Expedite premium IDR 186 m is below the IDR 250 m cap and below the IDR 214 m liquidated damages exposure.
S. Halim (Procurement Lead) · 12 Aug 2026, 14:30 UTC
Actor holds Procurement Lead role scoped to PTU-2026-017; requested spend IDR 186 m is within the delegated cap.
Outcome verification — NOT EFFECTIVE
Expedited MR-01 arrives no later than 26 Sep 2026
Criteria: Supplier declares a forecast on or before 26 Sep 2026 and goods receipt is recorded by that date
Verified by Readiness Engine · 14 Aug 2026, 08:15 UTC
Open decision archaeology- SYSTEM RECORDEV-3009Expedited freight booking AWB 172-88410233TMS · 13 Aug 2026, 11:02 UTC · sha256:ev3009…
- EMAILEV-3007Meridian Switchgear revised forecast 12 Oct 2026 (supersedes EV-3005)MAIL · 13 Aug 2026, 16:12 UTC · sha256:ev3007…